Kenya Electricity Generating Company (KenGen) has completed a three-year rehabilitation of Olkaria I, the country's oldest geothermal power station, increasing its generating capacity from 45 megawatts (MW) to 63.3MW.
The upgrade restores an additional 18.3MW of generating capacity to the national grid, strengthening Kenya's domestic electricity supply as demand from households, businesses and industries continues to grow.
KenGen Managing Director Peter Njenga announced the completion on November 25, 2026, in Naivasha, Nakuru County. The plant, which was commissioned in 1981, had been shut down in 2023 to allow extensive rehabilitation of its ageing equipment.
The project involved replacing major generating equipment, including turbines and generators across the plant's three units. Engineers also upgraded the steam-gathering system, cooling infrastructure, control valves and other components to improve operational efficiency and extend the facility's useful life.
The rehabilitation is expected to extend the operating life of the three units by more than 25 years. KenGen has put the investment at approximately Sh15.6 billion, forming part of its broader programme to modernise generation infrastructure and strengthen electricity supply.
The restored plant is undergoing reliability tests ahead of its official commissioning, which is scheduled for December 7, 2026. The completion therefore marks the end of the rehabilitation works, while formal commissioning remains pending.
The additional capacity comes as Kenya continues to rely on electricity imports to supplement domestic generation. Kenya Power imported 1.91 billion kilowatt-hours of electricity in the year to June 2026, a 60.5 per cent increase compared with the 1.19 billion kilowatt-hours recorded in the year to June 2024.
Olkaria I's return will help reduce pressure on the national supply system by restoring generation from an existing geothermal resource without requiring the development of an entirely new power station.
The project also supports KenGen's wider geothermal strategy, which includes supplying electricity and steam to industrial investors at the Olkaria Green Energy Park. The company says the park has attracted investors, including a fertiliser manufacturer expected to require substantial geothermal energy.
For electricity consumers, the increased generation adds to available supply, although the rehabilitation alone does not guarantee lower electricity tariffs. The final impact will depend on generation costs, power purchase arrangements and the wider mix of electricity supplied to the grid.
KenGen's next priority will be completing reliability testing and commissioning the refurbished plant as it pursues further investments in geothermal and other renewable energy projects.